MRP Structure

Consider the bill of material for Product J and the data
given in the following table. The gross requirements for J are 200 units in
week 6 and 250 units in week 8. Develop the MRP tables for each item for an 8
week planning period. Use the lot-for-lot lot-sizing rule.

J is dependent on K(1) which is dependent on L(4)

J is dependent of M(2)

Item – Lead time – Quantity on Hand – Scheduled receipts

J 1 0

K 2 20 30
in week 2

L 2 0

M 1 20 10
in week 1

What is the planned orders for J in period 5?

What is the gross requirements for J in period 8?

What are the planned orders for K in period 2?

What are the planned receipts for K i period 7?

What are the planned order for L in period 1?